Publicly available information on official websites does not provide a clear basis to independently verify the reported figures on canal excavation and re-excavation progress stated by the Water Resources Minister. Available project-level data indicates that, as of February 2026, BADC has achieved 42.77 per cent of its FY2025–26 target, with no comparable consolidated progress data available for other implementing agencies. While multiple agencies, including BWDB, LGED, and others, are undertaking excavation and re-excavation activities across the country, information on their progress remains fragmented across different government websites and documents, many of which are not readily accessible in the public domain, limiting a comprehensive assessment of overall implementation.
Information on ongoing canal excavation projects is drawn from official documentation of the Bangladesh Agricultural Development Corporation (BADC) and reported coverage in news sources. Under BADC, several canal excavation and irrigation-related projects are being implemented, as reflected in the Monitoring Division’s Progress Review Meeting Document on Ongoing Projects and Activities under FY2025–26 up to February 2026. The Smallholder Agricultural Competitiveness Project (July 2018–June 2026) has a total allocation of BDT 384.21 crore with a target of 664 km of canal excavation. The Pilot Research Project for Irrigation Water Management and the Development of a Web-Based Information System in Bangladesh (July 2021–June 2026) has a budget of BDT 73.24 crore with a target of 15 km. The Barisal, Bhola, Jhalokathi and Pirojpur Irrigation Development Project (September 2023–December 2026) has a budget of BDT 384.91 crore with a target of 375 km. The Irrigation Development Project Using Groundwater in Chattogram and Cox’s Bazar Districts (July 2023–June 2028) has a budget of BDT 602.26 crore with a target of 525 km, while the Irrigation Development Project Using Groundwater in Sylhet District (June 2025–December 2029) has a budget of BDT 499.99 crore with a target of 326 km. The Irrigation Development Project of Khulna, Satkhira and Bagerhat (July 2025–June 2030) has a budget of BDT 499.82 crore with a target of 500 km. Additionally, the Project for Establishing Seed Multiplication Farms in the Southeastern Region of Bangladesh (March 2022–September 2026) includes a canal-related component with a target of 12 km, with a total budget of BDT 478.36 crore.